Lighting
Systems
Daniel
Y. Bedard, Patrick V. Latham, III, Andrew Paul Malizio, William R.
Nelson - Mona Electric Group, Inc.
Project
Name: 51 Louisiana Avenue, Washington, DC
Architect: HKS, Inc.
Engineer: TOLK, Inc.
General Contractor:
Clark Construction Group, LLC
A large part of the overall effect was the
use of projector lights that were precisely aimed using lasers to
reflect the beams off of mirrors in the top of the atrium to reach
specific points on the floor. The final touch to achieve the architect’s
vision of the structure was the installation of a complex dimming
and lighting control system that is programmed to operate the lights
in different sequences and levels of brightness to provide maximum
effect while adjusting for the ever-changing levels of ambient conditions.
Danny
Groht, Gary Lee, Gene Mills, Jacob Manoogian, Brooks McClain, Janie
Oliver - J.E. Richards, Inc.
Project Name: W Hotel
(Formerly Hotel Washington), Washington, DC
Architect: BBG-BBGM
Engineer: Joseph R.
Loring & Associates, Inc.
General Contractor:
HITT Contracting Inc.
The original building was built in 1917
and it was necessary to maintain the historical value of the building
while providing all of the upgrades. The chandeliers in the ballroom
and some of the lights fixtures in the lobby are antiques that were
retrofitted and installed by the craftsmen; all of the other fixtures
are new. From the spa to the restaurant to the roof top bar and every
floor in between every light fixture was installed with the utmost
concerned by the most skilled craftsman.
Chris
Cady, Mark Carter, Greg Cobaugh, Erin Hickman, Senesha Matokovich,
Tom Shannon - Singleton Electric Company, Inc.
Project Name: DC Court
of Appeals, Washington, DC
Architect/Engineer:
Beyer Blinder Belle
Engineer: Joseph R. Loring & Associates, Inc.
General Contractor:
Hensel Phelps Construction Company
Originally constructed in 1820, the DC Court
of Appeals building is one of the oldest buildings in Washington,
DC. The electrical work had to be laid out on the existing plaster
and brick structure which was then removed and then the electrical
rough-in installed. One of the most impressive aspects of this project
is the amount of work that was put in which is now concealed behind
plaster walls finished to look as they have for over a century. The
project consisted of over 110 different fixture types with multiple
custom colors and finishes from numerous different manufacturers.
The project is unique in the fact that the fixtures installed ranged
from art deco inspired chandeliers to refurbished historic wall sconces
to custom replications of historic light fixtures. Many fixtures were
removed and refurbished to their original condition. A number of fixtures
were replications of originals. The project also had three dimming
systems; two for the courtrooms and one for the site lighting. The
project also had an energy management system for lighting.
Jon
Bayeaux, Danny Lambert, Greg Miller, Steve Slagle
- T.A. Beach Corp.
Project Name: Montgomery
College Cultural Arts Center, Silver Spring, MD
Architect/Engineer:
SmithGroup JJR
General Contractor:
Bovis Lend Lease
The significant attributes to this project
includes house lighting that are incorporated in block walls, handrail
lights that were custom-made to fit around the egress areas, aisle
lighting that was incorporated into concrete. The theater outlets
for stage lighting are roughed in block walls powered by the main
dimmer boards. The lighting control system includes multiple switches
located in each control room for each theater. There is a section
in the theater that has removable seating where the mixing station
floor box is located for the control of the theater’s AV system.
The AV/microphone speakers are installed on the balcony level. The
upper level is provided with all the systems that are installed on
the lower level with the exception of floor boxes. A theater rigging
control for light battens were also installed. The design’s
objective was to have the conduit in the theater accentuate the steel
structures and have the light fixtures and theater lights that are
mounted on catwalk rails be the focal point of the theater.
Brad
Behm, Dave Pierce, Todd Ransom, Bill Rhodes, Ed Rhodes, Mike Spear
- Power Solutions, LLC
Project Name: Children’s
National Medical Center Inpatient Tower Fit Out, Washington, DC
Architect/Engineer:
HDR One Company
General Contractor:
HITT Contracting Inc.
In this project, all lighting, power and
controls were installed in conduit and compression fittings. The schedule
and noise level was compression and access to the job site was challenging
as no trades were able to use elevators for manpower and materials.
The CNMC project consisted of over 25 different styles of specialty
light fixture styles, ranging from fluorescent 2 x 4 lighting in patient
areas to the complicated LED panels, tubing and power color core LED’s
in the lobbies. A typical patient room consisted of 14 light fixtures.
Some of these fixtures were wall mounted in drywall while others were
ceiling. Multiple system and voltages were intertwined to provide
lighting on critical, emergency and normal power simultaneously to
the patient headwall unit. The headwall unit controls the four function
lights over the patient bed; three of which interface with the patient
pillow speaker for optimum patient lighting comfort. The lobbies were
constructed with low voltage lighting. Color changing LED’s
mounted in custom boxes anchor the elevator lobby. LED panels in the
ceiling portray the night sky as you exit the elevators.
James
Carson, Jeff Cowan, Demal Dzelalic, Shawn Mooney, Jeremy Nelson, Jay
Potts - J.E. Richards, Inc.
Project Name: Eisenhower
Theatre, Washington, DC
Architect: Quinn Evans
Architects
Engineer: Mueller Associates,
Inc.
General Contractor:
The Whiting-Turner Contracting Company
The balconies at Eisenhower Theater were
partially demolished and extended. The entire floor was reconstructed
and the plaster ceiling was salvaged and all of the lights were retrofitted.
The dimming system was relocated and retrofitted. The conduit paths
that feed all of the lighting circuits travel through the bowels of
the Kennedy Center. In the dressing room, the lighting is controlled
through a series of relays. Careful consideration had to be taken
when working with metals contractor and the mill worker.
Russell
Bloss, John Bozzel, John Jenkins, III, John Jenkins, Jr., Marty Reedy,
John Richards - J.E. Richards, Inc.
Project Name: 1801 K
Street, NW, Washington, DC
Architect: Skidmore,
Owings & Merrill
Engineer: Girard Engineering,
PC
General Contractor:
Jones Lang LaSalle Construction
The art wall consists of 3,240 individual
lights which can be digitally programmed to display any design. The
main lobby has 385 lights. There are 196 retractable lights to backlight
the marble wall in the elevator lobby and 294 barrosae ceiling lights.
Façade lighting consists of up lights, 47 remote ballast, LED
lighting in stainless steel trough with 11 remote ballast.
Power
Generation, Distribution and Switchgear
Donnie
Beach, Eddie Bihlear, Devon Gaylor, Rich Ladow, Kenny Muschette, Ransford
Robinson - Truland Systems Corporation
Project Name: New Campus
East - Central Utility Plant, Springfield, VA
Architect/Engineer:
RTKL/KlingStubbins
General Contractor:
Clark/Balfour Beatty NGA, A Joint Venture
Truland Systems Corporation provided the
Central Utility Plant’s 34.5 Kv electrical system; which provides
permanent power for New Campus East’s mechanical equipment,
lighting and other building systems. Truland delivered superior workmanship
and integrated design services despite challenges including a compressed
schedule, a developing and complex design, limited and congested work
areas, coordination with multiple trades and the magnitude of the
project. The system components include 34.5 Kv, 5 Kv and medium voltage
systems as well as interconnected power distribution units.
Bill
Figgers, Joe Fuentes, Doug Leggat, Roy Meyer, Andrew Talcott, Walter
Williams - Dynalectric Company
Project Name: New Campus
East - Technology Center, Springfield, VA
Architect/Engineer:
RTKL/KlingStubbins
General Contractor:
Clark/Balfour Beatty NGA, A Joint Venture
The Technology Center’s electrical
system is notable for its exceptional craftsmanship, massive size
and the challenges presented by exterior factors, including a compressed
schedule, complex design, limited and congested work areas and coordination
with multiple trades. The system components include 34.5 kilovolt,
408 volt, and low-voltage systems including multi-module and rotary
UPS systems and power distribution units all connected by a large,
complex network of EMT conduit and busway.
Chet
Gagnon, Andy Hartnett, Ignacio Luna, Doug Thomas, George Wicks, Nick
Young - Young Electrical Contractors, Inc.
Project Name: POD-3
Renovation, Suitland, MD
Architect/Engineer:
EwingCole
General Contractor:
Clark Construction Group, LLC
A 6,380 square-foot penthouse was built
to house all of POD-3’s mechanical equipment. Coordinating the
different systems during installation was a challenge. Young Electrical
Contractors worked with all project team members and carefully pre-planned
the meticulous and methodical installation of all six separate MEP
systems, which occurred without errors. Because of the systems’
custom designs and space limitation, Young Electrical workers bent
and handcrafted all electrical conduits on-site. Though the POD-3
facility is a storage building that won’t be seen by the public,
Young Electrical paid close attention to the spaces aesthetics. The
high level of craftsmanship allowed for successful functionality of
the systems which will ensure the valuable treasures within are kept
in mint condition.
Philip
Boyd, Sam Brogan, Mark Eriksson, Kevin Patterson, Shane Sparks, Ben
Staniewicz - Truland Walker Seal JV
Project Name: Washington
Metropolitan Area Transit Authority Traction Power Upgrade Program,
Washington, DC
Engineer: Parsons Transportation
Group (P2D)
General Contractor:
Truland Walker Seal JV
The traction Power Upgrade program involved
rebuilding 33 traction power stations located throughout the Metrorail
system at the aggressive rate of one per month. Each substation was
unique because they were built at different times using equipment
from several different manufacturers who used proprietary design criteria.
Additionally, the new equipment was integrated with existing equipment
in the rest of the system. Truland Walker Seal JV rebuilt the substations
without disrupting daily service by coordinating with WMATA and PEPCO
and Dominion Power and performing most of the work during the four
to five hours Metro was not in service. Crews worked in difficult
conditions often deep underground or beneath major traffic arteries.
Joe
Dugan, Joseph Lajoie, Eric Neville, Nick Noonan, Russel Way
- Freestate Electrical Construction Company
¶
Project Name:
National Institutes of Health: CIT
Building No. 12 - Infrastructure Upgrade - Phase 1, Bethesda,
MD
Architect: Ann Myers
Architecture
Engineer: WFT Engineering,
Inc.
General Contractor:
Tishman Construction Corporation
The key to the project was to determine
how to install 9,6000 feet of feeder conduit, 300 feet of 2500-Amp
copper busway and 200 feet of 5000-Amp copper buss way, HVAC ductwork,
pre-action fire suppression system and a fire detection systems in
a ceiling space of three and half feet. Freestate Electrical installed
the electrical design for the new UPS which consists of three incoming
15 KVA services to a main distribution switchgear. The switchgear
consists of an A side main and B side main. The center main is connected
via tie breakers to the A and B side of the gear achieving one common
bus. There are two generator paralleling gears, PSG-A and PSG-B. Each
gear consists of three sets of electrical bus—a No-Break bus,
a Short-Break bus and a Common bus connecting the two choke reactors
at either end of the PSG boards. Both PSG boards are connected via
a 5,000 Amp cross link bus way. The four choke reactors are fed from
the utility MDS gear via a 2,500 Amp bus way and from two Continuous
Power System (CPS). The CPS units are synchronous condenser/ ac-motor
unit which supply a leading power factor to compensate for the potential
lagging power factor on the utility. There are four 3-source Digital
Static Transfer Switches. Two sources are from the PSG-A, B boards
and the third is from the utility board. The load side feeds distribution
boards T1-T4.
Star
Award Winner for Excellence in the Face of Adversity
David
August, Robert Daigle, Chuck Knaack, Glenn Laser, John M. Thir, Jr.,
Markco Yates - Natelco Corporation
Project Name: Silver
Spring Data Center UPS Replacement, Silver Spring, MD
Architect: Arium AE
Engineer: CCG Facilities
Integration, Inc.
General Contractor:
Holder Construction Company
Many aspects of this project made it particularly
difficult and the work exceptional. All power wiring was designed
to be run overhead but due to weight limitations, it was necessary
to install an underground duct bank system. This entailed saw cutting
and excavating the inside of the existing data facility. The duct
bank system was design in the field including intercepting existing
medium voltage feeders. Natelco performed five levels of commissioning
including factory witness testing in Germany. Crews installed a three
tier battery rack system which consisted of 369 battery jars to be
unloaded, stored and hoisted up on the racks. The most difficult part
of the job was intercepting three critical load buss ways over the
existing data center floor without loss of critical load or redundancy.
Mike
Caffrey, Dwight Daniels, II, Mike Johnson, Garth Kelly, Ha Le, Robert
Stephens - Singleton Electric Company, Inc.
Project Name: Arlington
County Water Pollution Control Panel, Arlington, VA
Architect/Engineer:
Malcom Pirnie
General Contractor:
Fru-Con Construction Corporation
This project included modernization of aging
infrastructure. Crews increased capacity from 30 million gallons a
day to 40 million gallons of treated waste water, generation of fewer
odors, and discharge of cleaner water to the Four Mile Run (Potomac
River) in compliance with strict EPA regulations to ensure a safe
and healthy environment.
Jeff
Hicks, Randy Higgs, Eric Johnston, Buddy McDowell, Cordelia McKoy,
Richie Roberts - Power Solutions, LLC
¶
Project Name:
Amazon.com IAD6 Pod7, Ashburn, VA
Engineer: EYP
Power Solutions installed two 3,000 Amp
switchboard, one of which was for mechanical equipment feeding one
850-ton chiller, one 1,000-ton cooling tower, sixteen crac units and
miscellaneous pumps and exhaust fans backed by a 2.00 megawatt generator.
The Critical switchboard feeds four 750 KVA UPS’s complete with
emergency battery backup systems, fourteen 225 kva PDU’s, numerous
panels backed by one 2.25 megawatt generator. The Data Room has cable
tray containing 15,000 feet of #8 branch circuit wiring with 700 L6-30R
receptacles feeding the individual racks. After a considerable amount
of coordination with the power company, all work was completed within
a very aggressive eight week schedule. The dedicated craftsman worked
numerous hours of overtime to accomplish this feat. The job peaked
at approximately 30 electricians.
Eric
Figueroa, Thomas Gregory, Kyle Murphy, Elwood Ness, Steve Rivera,
Dwight Williams - J.E. Richards, Inc.
Project Name: IBM-NCEP
Phase 4, Gaithersburg, MD
Architect/Engineer:
McKinney & Company
General Contractor:
Skanska USA Building
All work was completed and commissioned
within a 14-week schedule. Work included receipt and installation
of two 1,000 KW generators, paralleling switchgear; two 1,500 KVA
substations (13.2KVAC-480VAC); two 500 KVA UPS units with bypass;
ten static transfer switches and two Power distribution units. Work
also included power distribution using Bus Duct and conduit and wire.
All work was completed within an operational office and Data Center.
Special
Systems (including security, control
& instrumentation)
Mike
Buser, Kevin Cole, Kyle Priddy, John Zanelotti - Ennis
Electric Co., Inc.
Project Name: New Campus
East - Technology Center, Springfield, VA
Architect/Engineer:
RTKL/KlingStubbins
General Contractor:
Clark/Balfour Beatty NGA, A Joint Venture
An integral part of the National Geospatial-Intelligence
Agency’s New Campus East, the Technology Center is a 125,000
square-foot data center that will support all electrical components
and house the NGA data storage facility for classified information.
The Technology Center’s fire alarm and mass notification systems
are one-of-a-kind, first edition systems combined multiple vendors
and products in one complete system. The design and contractual set
up for Ennis Electric required the company to mate two fire alarm
vendors to the same system. This required hours of re-writing code
and coordinating between vendors to produce the fire alarm system
that will transmit signals via transmitter antenna from New Campus
East to Fort Belvoir’s main fire station.
Brian
Cramutola, Kathy Freeland, John Kassmer, Jeff Marshall, Shawn Samii,
Ray Scheuring - Diversified Systems
Project Name: Teleproductions
International, Chantilly, VA
Architect: Gileau-Poulton
Architects and Associates, PC
Engineer: Diversified
Systems
General Contractor:
Forrester Construction Company
The AV installation of Teleproductions International
included numerous audio and video editors, central equipment room,
live production control room, sound stage, in-house SMATV system,
multiple conference rooms, 28-seat auditorium and installation of
a small antennae farm. Diversified Systems evaluated a variety of
standards and current workflow processes and made suggestions that
were accepted to improve the performance of the system. These included
adding the storage area network and relocating all servers to a central
equipment room while maintaining the integrity of sound proofing and
sound dampening in the recording and editing areas. Installers developed
practical details for routing conduit, as well as accurately maintain
and route over 8,000 cables of varying types from 75 ohm coaxial to
high speed fiber. The runs spanned roughly 150 feet on the second
floor back to the central equipment room and runs that spanned 60
feet from the central network room to editing, control and capture
points.
Brian
Baniszewski, Mike Brawner, Edwin Lugan, Scott Ponton, Dave Thorne,
Bob Wood - Freestate Electrical Construction Company
Project Name: Goodwin
House Bailey's Crossroads, Falls Church, VA
Architect: Dorsky Hodgson
Parrish Yue Architects
Engineer: KTA Group,
Inc.
General Contractor:
The Whiting-Turner Contracting Company
The fire alarm system at Goodwin House retirement
facility is critical to staff, residents and guests. The existing
system was obsolete and becoming difficult to maintain and expand
to new construction projects, so the system was replaced while the
building was fully occupied. Freestate teamed with Alarm Tech Solutions
to replace the old system on a floor by floor basis. Crews changed
over the controls and status of all of the components of the smoke
control and stair pressurization systems as well as all initiating
devices while reusing as much circuit wiring as possible. New riser
wiring was installed in existing conduits to facilitate a changeover.
New remote power expander panels and amplifier cabinets were installed.
After the emergency replacement of existing fire alarm and emergency
communications system, Freestate and Alarm Tech went on to do the
fire alarm, gas detection and emergency communications for the Health
and Wellness Center and the new Independent Living Tower.
Kenneth
P. Bremerman, Donte M. Jackson, Thomas Jason Kite, Charles R. Martin,
Jr., David W. Moore - Mona Electric Group, Inc.
Project Name: Columbia
Square, Washington, DC
Engineer: WCIS Consulting,
LLC
General Contractor:
K3 Construction Group
This fire alarm project consisted of a system
head end panel replacement. AV devices were added throughout the facility
to provide complete system notification. There was a smoke removal
system with 157 dampers that was partially decommissioned during this
project. All fire alarm controls and relays were removed for 104 of
the smoke dampers. This decommissioning had to take place during system
changeover. There remained approximately 53 smoke exhaust dampers
with panel and detector control and 50 control switches for building
fans. The craftsmen installed the new system back bone parallel to
the old system in the FACR, reusing existing floor wiring. The crew
worked night shift and changed over floor by floor.
Aaron A. Day, Bernard A. Johnson
- Mona Electric Group, Inc.
Project Name: Willard
Intercontinental, Washington, DC
This fire alarm project consisted of a system
head panel replacement for both buildings at the Willard InterContinental.
The Office tower and hotel had separate control panels but were located
in the same fire control room. Crews spilt up the two systems and
replaced the field initiating devices with addressable devices utilizing
the existing IDC circuits as a signaling line circuit. The craftsmen
installed the new system equipment adjacent to the old system in the
FACR. With the existing floor initiating wiring being reused as the
SLC loop, device changeover had to occur on a floor by floor basis.
Once a floor changeover started, the crew could not leave the job
until all devices on the loop were on the new system.
Robert
Drescher, Tanya Filkins, Chris Harper, Richard Mercer, Gregory Ward,
Jon Whiston - Dynalectric Company
Project Name: Alexandria
Powerhouse Recovery Project, Alexandria, VA
Architect/Engineer/General Contractor:
Mirant
This was a pilot project for all coal burning
power distribution plants in the world. It has been nominated for
a Platt Global Award. In ten weeks, Dynalectric worked 25,000 hours
to install 29 miles of cable. Damper motors, monitoring fan controllers,
Beck and Rexa actuators located from below sea level to air stacks
250 feet above ground control ten 4160 volt induced draft for units
which push exhaust through a redesigned duct system consolidating
all exhaust gases from five stacks to two through
a Trona system that will reduce emissions.
Telecommunications
Systems & Facilities
Finishes
Ceramic
Tile and Terrazzo
Lakesha
Coates, Telly Koutris, Vince McCoy, Victor Rodriguez
- David Allen Company
Project Name: Constitution
Center, Washington, DC
Architect: SmithGroup
General Contractor:
James G. Davis Construction Corporation
The Constitution Center renovation involves
a complete renovation of the original 10-story, 2.1 million square-foot
facility. The scope of work included removal of the envelope and interiors
to its original structure, installation of a new blast rated floor-to-ceiling
curtainwall system, 36 new typical floor cores, 31 elevators, 50,000
square feet of plaza level lobbies a one-acre outdoor courtyard, restoration
of the 15-acre parking garage and a new penthouse structure and MEP
plant. This project is expected to achieve LEED Gold certification.
David Allen started tile work in the NE core with a mockup of one
bathroom for the entire project team’s review. David Allen then
worked the NE core down to completion and moved counterclockwise to
the SE core. David Allen worked through many obstacles, the largest
being the weather. Without a complete curtainwall, David Allen worked
in confined bathrooms with small heaters so that the mastic and grout
could set. As the leaders driving the bathroom schedule, David Allen
overcame the weather as well as leveling challenges and existing conditions
to push the project to completion.
Keith
Oliver - David Allen Company
Project Name: Georgetown
University McDonough School of Business, Washington, DC
Architect: Goody Clancy
Associates
General Contractor:
The Whiting-Turner Contracting Company
The work that David Allen did in the atrium
of the Georgetown University McDonough School of Business included
epoxy terrazzo flooring and the pre-cast Portland cement terrazzo
stair treads. Both feature prominently in the signature space of the
building. They did a great job matching the treads with the flooring,
even through they were made of two different materials. The epoxy
terrazzo flooring consists of alternating strips of two colors through
the atrium lobby. The pre-cast treads installed as the feature stair
were cast with a weld plate of the bottom and were welded to the steel
tubes that service on the spine of the stair. They do not sit in a
pan like most of these types of installation. The installation of
the treads provide to be especially difficult when the tubes deflected
more than expected, but David Allen worked tirelessly to deliver a
breathtaking “wow” moment when you enter the atrium. This
project is striving for LEED Silver certification.
Carlos
Cumes, William Gray, Phillip Jones, Limbert Perez, Sang Yun, Ung Yun
- Ward Ceramic Tile & Stone, Inc.
Project Name: Potenza
Trattoria Bakery & Wine, Washington, DC
Architect: CORE
General Contractor:
Forrester Construction Company
Upon starting construction of Potenza Trattoria,
Bakery & Wine, the floors were at varying heights throughout the
space. Considerations were made to create a consistent floor height
as well as transition to an historic hallway between the bakery and
trattoria. Ward Ceramic Tile installed a mud bed under each type of
floor tailoring the mixture to the thickness and type of material
being used. Various flashing agents and latex additives were used
to create the necessary height and slope of the tile substrate for
tile installation. The types of tiles specified in the project included
ceramic, stone, encaustic and marble. Oval link stone mosaic tile
installed in the bakery was custom from China. Encaustic tile installed
throughout the trattoria and bakery was specified in a variety of
colors and patterns and was custom from Mexico. A unique pattern of
crackle glazed subway tile was installed in the bakery and brick colored
quarry paver mosaic was installed on the large pizza oven. To ensure
the correct patterns were achieved, nock ups were prepared daily and
became a pivotal part of the title installation process. The patterns
required a remarkable amount of prep work and lay out to ensure the
Architect’s vision.
Lakesha Coates, Vince McCoy, Telly Koutris,
Victor Rodriguez - David Allen Company
Project Name: Tyser
Tower Renovation and Expansion, College Park, MD
Architect: Heery International,
Inc.
General Contractor:
Clark Construction Group, LLC
The Tyser Tower Renovation and Expansion
project is a 66,000 square-foot addition and complete renovation of
the 33,000 square-foot Tyser Tower, located at University of Maryland’s
(UMD) Byrd Stadium. One of UMD’s major stipulations was a high-quality
installation of tile in the restrooms throughout the building to eliminate
minor flaws common in tile installation—small slivers of tile
in the corners, tiles that are not perfectly square, grout joints
that are not uniform, and floor drains placed randomly in the floor.
David Allen worked to extremely tight tolerances during the tile installation
while meeting a demanding schedule. Public bathrooms include a cross
tile, manufactured by David Allen, with the Terps logo, while suite
bathrooms feature a red glass mosaic pattern. To distinguish the President’s
Suite, the bathroom follows a black and red granite scheme and the
water jet was produced in Atlanta and numbered for installation. This
glass-like pattern required minimal grout joints for installation.
To eliminate drain location problems, structural floor slabs were
constructed using two-foot square opening at the planned location
of each drain. As final drain locations were identified, David Allen
set them to fall within the tile pattern, which took considerable
time and effort. The end result is well above industry standards.
Carlos
Amaya, Miguel Flores, Lisandro Guevara, Tom Hess, Jose Rivas, Mike
Trevisan - Roman Mosaic and Tile Company
Project Name: Crystal
Plaza II, Arlington, VA
Architect: Dorsky Hodgson
Parrish Yue Architects
Structural Engineer:
Tadjer Cohen Edelson Associates, Inc.
MEP Engineer: GHT Limited
General Contractor:
Balfour Beatty Construction
From behind the walls of the building to
the imposing atrium lobby, exceptional care and craftsmanship went
into constructing this high-end renovation of Crystal Plaza II. Much
of what sets this project apart is the work provided by Roman Mosaic
and Tile Company who installed epoxy and custom precast terrazzo flooring
throughout the lobby. Roman Mosaic overcame many unique obstacles,
from installing the spiral floor pattern layout based solely on a
rendering (no dimensioned plans), to extensive sand-fill to repair
slab conditions for the existing 40-year-old floors. Most notable
was the installation of the custom precast terrazzo on the lobby’s
grand staircase. Due to complex curves, shapes and tight dimensional
requirements, each piece had to be custom cast, cut and carefully
placed. In addition, the precast terrazzo had to interface with a
custom, curved-glass railing, which required multiple stages of installation
and extensive coordination.
Drywall (including
framing & finishing)
Jose
Alba, Tony Cassette, Tommy Hurlock, Fred Jackson, Roger Marsden, Jose
Perez - C. J. Coakley Co., Inc.
Project Name: Constitution
Center, Washington, DC
Architect: SmithGroup
General Contractor:
James G. Davis Construction Corporation
The Constitution Center renovation involves
a complete renovation of the original 10-story, 2.1 million square-foot
facility. The scope of work included removal of the envelope and interiors
to its original structure, installation of a new blast rated floor-to-ceiling
curtainwall system, 36 new typical floor cores, 31 elevators, 50,000
square feet of plaza level lobbies a one-acre outdoor courtyard, restoration
of the 15-acre parking garage and a new penthouse structure and MEP
plant. This project is expected to achieve LEED Gold certification.
Coakley was involved in every aspect of drywall, ACT, plaster, metal
reveals, fabric ceiling panels, and exterior framing. The drywall
was a major factor of the layout and control for all follow up trades.
The most impressive portion of the project is how consistent Coakley
was throughout all areas of project- having 80+ workers onsite during
its peak. Coakley set up Constitution Center like a high rise building
and started in the NE core working down nine floors and then moved
counterclockwise ending in SE core. At the same time, they worked
around the 50,000 square-foot plaza level where the highlight is a
continuous concourse that connects the NE lobbies all the way to the
SW lobbies.
Steve
Biniek, Luis Ramirez Guzman, Oscar Guzman, Abel Romo, Everado Romo,
Leopoldo Romo - Capitol Drywall, Inc.
Project Name: The Georgetown
Preparatory School New Learning Center, North Bethesda, MD
Architect: Cox Graae
+ Spack Architects
General Contractor:
The Whiting-Turner Contracting Company
The work at Georgetown Preparatory School
New Learning Center consisted of the renovation of the existing field
house and a new building addition. A 44-foot by 5-foot skylight was
cut into the existing roof roughly 28 feet above the new finished
floor in the new Library. Capitol Drywall installed new multi-tiered
ACT, wood and sound panel and drywall ceilings. The drywall installation
and finishing posed significant challenges. The new ceiling slopes
up on four sides from an elevation of 16 feet. In addition, the ceiling
was turned on a 10 degree angle to the East-West axis of the building
order to align with the architectural elements that carry through
both the new and renovation work. Capitol Drywall performed layout
on the concrete slab and transferred the layout up to multiple elevations.
They then determined how to coordinate the required ceiling framing
members with the existing steel cross bracing and trusses. Finally,
due to the significant exposure to sunlight throughout the day the
finish work had to be of the highest quality to make the gypsum board
joints, screw heads and other imperfections disappear.
Earl
Ferguson, Sean Rigsby, Tim Rigsby - Cleveland
Construction
Project Name: Arena
Stage at the Mead Center for American Theater, Washington, DC
Architect: Bing Thom
Architects
Engineer: Fast + Epp
General Contractor:
Clark Construction Group, LLC
The renovation and expansion of the Arena
Stages performing arts campus in Southwest DC covered 200,000 square
feet and took 29 months. It included the creation of a new performance
arts space, the Cradle Theater, and extensive improvements to the
existing buildings. The new Arena Stage will be a largely transparent
structure under a prominent cantilevered roof. The sleek and amorphous
roof design creates the illusion of wave-like movement. Using light
gauge framing, Cleveland Construction successfully executed the architect’s
vision for the roof overhang and terrace soffit. The overhang undulates
as it wraps around the perimeter of the building. In the northwest
corner, it expands over the terrace and out to a cantilevered point.
To create this effect, the framing in the northwest corner had to
be installed to accommodate the deflections in the cantilevered roof.
The expansive soffit and sloping corner is interrupted by control
joints designed for movement and aesthetics. Cleveland Construction
worked off lifts to get to the overhang and soffit and will use lifts
to finish the soffit with acrylic stucco. The geometry made layout
and framing difficult, but limited access to the overhang made the
work even more complicated.
Fernando
Alvarado, Desi Crooks, Roberto Diaz, Carl Hoffner, Jorge Portillo,
Dennis Urias - S. DiGregorio & Son, Inc.
Project Name: Wyndham
at National Harbor, Oxon Hill, MD
Architect: WDG Architecture,
PLLC
Engineer: GHT Limited
General Contractor:
Balfour Beatty Construction
S. DiGregorio & Son furnished and installed
drywall throughout Capital Cove, including the main lobby, pool area
and sales office. The scope of work consisted of structural and interior
studs, dense glass, gypsum wallboard walls and ceilings. The results
are flawlessly finished, long corridors with chair rail and light
fixtures smoothly spanning more than 300 feet in length. The drywall
is perfectly aligned with all joints hidden from sight—evidence
of exceptional skill and attention to detail. The same seamless results
were accomplished with the ceilings in the indoor pool area, outdoor
breezeway and sales office. The ceilings were finished with a high-gloss
paint, which really shines a spotlight on the high-end results DiGregorio
delivered.
Flooring (including
wood, carpet & resilient floor tile)
Painting & Wallcovering
Danielle
DeFrancisco, Joe Hartlove, Sebastian Montano, Juan Morales, Selvin
Morales, Magarito Vargas - NLP Enterprises, Inc.
Project Name: The Jefferson
Hotel Renovation & Revitalization, Washington, DC
Architect: ForrestPerkins
General Contractor:
SIGAL Construction Corporation
NLP Enterprise’s painted the drywall
walls and ceilings and field painted the paint-grade millwork. The
color and material schedule for the project had 174 paint types listed.
All of the guestroom walls required multi-color wall treatment that
varied depending on the floor and scheme. Everything, including device
cover plates, was painted. There are 99 guest rooms in the hotel with
24 different colors that were applied in various arrangements depending
on the room scheme. These colors, and the 12 new colors for the public
areas on the basement and first floors, created a complicated web
of colors and paint types for the painter to keep track of. NLP successfully
accomplished the task with no errors due to wrong paint or color application.
Arturo
Beltran, Cesar Echevarria, Jonathan Echevarria, Roberto Echevarria,
Ivan Fitz, Nelson Martinez - Precision Wall Tech,
Inc.
Project Name: Georgetown
University McDonough School of Business, Washington, DC
Architect: Goody Clancy
Associates
General Contractor:
The Whiting-Turner Contracting Company
The craftsmen for Precision Wall Tech took
great care in applying the polymix finishes throughout the Georgetown
University McDonough School of Business. Rarely does one see so much
polymix applied on a project with the resulting evenness and consistency
throughout. It is apparent that this project was completed by very
skilled craftsmen as this “liquid wallpaper” is not easy
to apply. This project has been submitted for LEED Silver certification.
Plaster
(including Stucco and Dryvitt)
Raymond
Andrews, Nathan Bell, Jimmy Pryor, Mike Robb, Billy Underwood, Jeff
Zeman - John H. Hampshire, Inc.
Project Name: Alice
Deal Middle School, Washington, DC
Architect: Quinn Evans
Architects
General Contractor:
Prince / Schlosser Joint Venture
The crew did a total restoration of lower
scored plaster matching existing walls. All of the ornamental plaster
ceilings and walls were restored to match the existing. Casting of
existing ornamental plaster was required for a large portion to be
duplicated to restore the ornamental plaster to like-new conditions.
Restoration of all cornice and bands and installation of new acoustic
plaster above and below balcony was also done.
Shirlon
Elvis Maynard, Daniel McLean, Ceasar Philpot, Bruce Tomaselli
- Office of the Architect of the Capitol
Project Name: House
Office Buildings Sprinkler Installation, Washington, DC
Construction Division painters and plasterers
worked carefully and methodically to provide a seamless finish in
conjunction with the Construction Division plumbers as part of the
House Sprinkler project. The project required extensive coordination
with the House Superintendent’s Office and involved plastering
and painting of intricate and historic spaces in buildings of great
historical significance. Safety and preservation of the existing structure
was a key priority and the AOC Construction Divisions highly-skilled
plasterers paid attention to every detail. The plasterers expertly
constructed molds old the existing plaster to recreate the patterns
and details of the molding accurately. The seamless construction and
painstaking attention to detail are indicative of how the AOC Construction
Division approaches all projects.
Edwin
Castellon, Henry Castellon, Serge Vadenoff - Senza
Finé
¶
Project Name: Teleproductions International,
Chantilly, VA
Architect: Gileau-Poulton
Architects and Associates, PC
General Contractor:
Forrester Construction Company
The concept of this project was to completely
renovate an existing space and create a truly state of the art audio
visual recording, editing and production facility with a visually
refined atmosphere to compliment the technical precision of the space.
Throughout the building, various colors of Armourcoat plaster were
used to create a hand-trowel Venetian marble and a dragged finish
to this end. The artisans seamlessly completed a continuous wall-
approximately 200 feet long by nine feet tall- in six bands of finish,
three dragged and three Venetian. This area spanned two entrance lobbies
and the main corridor of the building and included many 90 degree
turns to complicate the work. In addition, a dragged Armourcoat finish,
nine feet wide by 20 feet tall was used in the main stairwell landing
which incorporated a polished TPI logo, a particular accomplishment
with all of the acute edges and size of the logo.
Specialty Painting
Eddy
Bustos, Walter Chavez, Marvin Hurtado, Josias Sanchez, Jeff Storm
- Brien A. Miller Painting Co., Inc.
Project Name: Headquarters
of the American Pharmacists Association (APhA), Washington, DC
Architect: Hartman-Cox
Architects
General Contractor:
Tishman Construction Corporation of DC
Brien A. Miller Painting Company furnished
and installed a wide variety of paints, sealers and wall coverings
for a new 10-story, 353,000 square-foot office building and parking
garage. Central to the site is the historic “Pope Building”
positioned adjacent to the new building. Miller Painting refreshed
and repaired aged wall finishes with modern products and techniques
while maintaining the building’s historic ambiance. Miller Painting
instituted a second shift from 3pm to 12am. Thanks to Miller Painting’s
efforts, more than 118 owner-initiated modifications without impact
to the schedule. The two underground garage levels were striped and
sealed, walls were painted using laser levels and fire suppression
systems were color-coded. Each of the eight tenant-occupied levels
included application of traditional paints, spray-applied Polymyx
and vinyl wall coverings. The focal point of the new addition is the
main lobby, where two different faux finishes were applied. The first
seamlessly imitates the Andes Gray marble on the floor and columns.
The second replicates a wall covering that was originally found within
the Pope Building. All paints, primers, adhesives and sealers were
low-VOC, enabling the project to work toward LEED Gold certification.
Masonry
Exterior
Stone
(including
marble, granite & exterior pavers)
Eric
Holloway, Francisco (Paco) Lorenzo, Jose Lopez, Jose A. Marquez, Johny
Reyes, Cipriano Vidal - Lorton Stone, LLC
Project Name: Howard
Hughes Medical Institute Headquarters Expansion - Phase II, Chevy
Chase, MD
Architect: Bowie Gridley
Architects
General Contractor:
Clark Construction Group, LLC
To maximize energy efficiency at Howard
Hughes Medical Institute headquarters, stone eyebrows were placed
above office windows to provide shading. In addition, the granite
helped increase daylighting, contributing to several LEED credits.
The circular feature space of the building is clad in curving limestone
panels. Approximately 436 tons of limestone equating to nearly 20
truckloads of cut stone for a total of 3,237 pieces was used. The
central space is accented with a fieldstone-clad full height interior/exterior
wall. The tedious and detail-oriented fieldstone work carries through
the site in the many stone-clad retaining walls.
Vital
Cardoso, Manuel Dobarco, Mario Guzman, Martin Lucio, Jose Neves, Mark
Sanders - Lorton Stone, LLC
Project Name: Semper
Fidelis Memorial Park Chapel, Triangle, VA
Architect: Fentress
Architects
Engineer: Ammann &
Whitney
General Contractor:
Forrester Construction Company
The rubbed stacked stone that adorns Semper
Fidelis Memorial Park Chapel and the restroom buildings on site all
hand chiseled stones from Western Maryland. Each piece was selected
to provide a consistently random appearance. Special care was made
to limit the amount of split face on exterior to maximize the percentage
of natural stone edges. Therefore, a high amount of stone was rejected
to maintain this level of quality control while providing a “slapped-together”
look. Lorton used a new, innovative corrugated weep drainage system
and an advanced stone tie system resided behind the rubble stone.
Lorton’s designers created 3-D models to determine coordinating
the multiple radii and slopes that existed in the exterior granite
hardscapes, water feature and tied into the interior granite flooring
and coordinated with the concrete contractor. The end result included
tight radii, smooth transitions and a striking appearance.
Interior
Stone & Marble
Michael
R. Patterson, Juan J. Rodriguez, Ronald S. Wondoloski
- Boatman and Magnani, Inc.
Project Name: The Jefferson
Hotel Renovation & Revitalization, Washington, DC
Architect: ForrestPerkins
General Contractor:
SIGAL Construction Corporation
Boatman and Magnani’s stone, ceramic
and quarry tile work included both thinset and mudset installation
of stone floors and walls at the guestroom and public spaces; mosaic
inlays at the North Hall and Presidential Suite; stone treads at the
Grand Stair; and custom carved stone fireplace mantels and columns.
Stone setters were challenged to bridge between the different substrates
and install a floor that was warrantable and will stand the test of
time. The existing perimeter and core walls were also out of square
and level so this also provided a challenge to installing wall tile
and base in a manner that would hide deficiencies in the existing
structure.
Unit
Masonry
Terry
Bricker, Nathan Delabar, Westley Douglas, Fernando Torres, Rudy Torres
- Manganaro Midatlantic, LLC
Project Name: Howard
Hughes Medical Institute Headquarters Expansion - Phase II, Chevy
Chase, MD
Architect: Bowie Gridley
Architects
General Contractor:
Clark Construction Group, LLC
The majority of the building envelope on
the Howard Hughes Medical Institute headquarters is masonry veneer
with substantial elements of granite and limestone sills, headers
and trim pieces integrally set within the masonry. A custom mix of
brick was created in order to match the existing facility, which was
a challenge. Some notable features include special shape window jamb
bricks, recessed decorative panels, a large masonry arch, a variety
of different bond patterns and coursings (Flemish, running soldier,
etc).
Scott
Bryan, Jose Cruz, Greg Dodson - Karon Masonry
of Maryland
Project Name: St. Elizabeths
New Hospital, Washington, DC
Architect: EYP
General Contractor:
Tompkins Builders, Inc.
St. Elizabeth’s Mental Health Facility
is exceptional because of the consistency of the craftsmanship on
such a large project. This is one of the largest masonry projects
built on the east coast in five years. Over 1.7 million brick and
1 million cinder blocks were used in the facility. In addition to
meeting LSDBE requirements the project was built on time and on budget.
Implementing two masons starting from opposite ends of the building
created a highly competitive atmosphere while upholding exceptional
quality.
Mechanical
HVAC-Controls
and Instrumentation
HVAC-Piping
Harold
Flowers, George Giddings, Don Mullens, Steve Owens, Tommy Tanner
- John J. Kirlin, LLC
Project Name: Hilton
Washington Guest Room Renovation, Washington, DC
Architect: OPX
Engineer: Leach Wallace
Associates
General Contractor:
The Whiting-Turner Contracting Company
This project involved the replacement of
six cooling towers and associated piping, pumps and the addition of
a new condenser water system to handle the new heat pumps in all 1,100
guest rooms. Work took place in a very tight area of the existing
penthouses, all while keeping the Hotel’s HVAC system on line
and operational.
Scott
Coble, Frank Davis, Brian Goodrich, Jack Leverstein, Kenneth Perigo,
Carl Proctor - JCM Associates, Inc.
Project Name: Howard
Hughes Medical Institute Headquarters Expansion - Phase II, Chevy
Chase, MD
Architect: Bowie Gridley
Architects
Engineer: Syska Hennessy
Group
General Contractor:
Clark Construction Group, LLC
The new HHMI Mechanical Plant was phased
into the existing campus and allowed for HHMI to maintain occupancy
of their facility, construct a new wing and convert their existing
HVAC system to one that was certified LEED Gold. Mechanical piping
and equipment layout/coordination was done using 3-D software to facilitate
accurate installation. The craftsmanship behind the piping installation,
pre-fabrication, coordination and completion is exemplary.
Dave
Bauer, Yunmy Carrol, Keith Fletcher, Brian Houser, Trent Jackson,
Ricky Stevens - W.E. Bowers, Inc.
Project Name: 1999 K
Street, Washington, DC
Architect: WDG Architecture,
PLLC
Engineer: GHT Limited
General Contractor:
James G. Davis Construction Corporation
This project involved the new construction
of a LEED Silver rated distinctive glass 12-story corner office building
and underground parking garage. Most of the mechanical equipment and
the heart of the HVAC system are located in a tight glass walled penthouse.
The building is conditioned by two massive Ventrol air handling units
utilizing new fan wall technology and concealed in roof mounted in
wells. The main two-level mechanical room includes two McQuay dual
compressor centrifugal chillers, nine base mounted pumps, UV disinfection
equipment, cartridge filtration and chemical treatment system. During
construction, the addition of a heat exchanger, pumps and associated
piping only added to complexity of the project. The limited space
required precise coordination and piping prefabrication. Of special
note was the sequencing of the equipment and pipe rigging because
there was limited staging area on the roof. The window of opportunity
was further restricted by the curtain wall construction. Care was
taken at all times to prevent damage to the unusual glass curtain
wall enclosing the penthouse.
Thomas
Athanason, Richard Cherba, Anthony Davis, Matthew Hill, Michael Spears,
John Tatro - Pierce Associates, Inc.
¶
Project Name:
Constitution Center, Washington, DC
Architect/Engineer:
SmithGroup
General Contractor:
James G. Davis Construction Corporation
Constitution Center has been completely
redesigned and modernized including state of the art upgrades in HVAC
systems, façade and controls and is on track to achieve LEED
Gold certification. As part of this retrofit, Pierce Associates’
steamfitters from UA Local 602 installed $7.5 million work of HVAC
equipment, including centrifugal chillers, cooling towers, boilers,
hydronic pumps and telecom closest fan coil systems, Also of note,
they coordinated and procured over 6,000 chilled beams to be used
for building climatization, the largest privately contracted use of
these systems in the region. All this was done in the confines of
the existing building’s structural limitations and completed
in a timely fashion at the highest industry standard.
HVAC-Sheet
Metal
William
Flaherty, Juan Luyo, David Nickless, Josh Nida, David Peak, Jr., Gary
Rawlings - Stromberg Metal Works, Inc.
Project Name: University
Biomedical Research Laboratory, Manassas, VA
Architect: RMJM
Engineer: Bard, Rao
+ Athanas Consulting Engineers, LLC
General Contractor:
The Whiting-Turner Contracting Company
The mechanical room is very congested and
required coordination and sequencing of work with other trades. This
project contains 102,000 pounds of galvanized duct and 98,000 pounds
of welded stainless steel ductwork. Unique and strict leak test requirements
allowed for little to no allowable leakage. Testing was required on
all ductwork to within inches of air devices and equipment. The system
design utilizes 200 air valves, 45 vav’s, 223 sound attenuators,
67 bubble tight dampers, 67 motorized dampers and 94 reheat coils.
Rod
Bates, Darius Canty, Robert Peliculinas, Marcus Tongue, Dale Werner,
Tony Wheeler - Southland Industries
Project Name: Walter
Reed National Military Medical Center (at National
Naval Medical Center), Bethesda, MD
Architect: HKS, Inc.
Engineer: Southland
Industries
General Contractor:
Clark Balfour Beatty JV
The sheet metal duct systems and prefabricated
double-decker style enthalpy wheel plenum panel sections in the basement
MER portion of this 533,000 square-foot medical office building was
very large and very complex. In addition, a lot of coordination/logistical
effort went into fitting these complex and large systems amongst other
MEP/Architectural systems in a compressed period of installation in
the basement of this facility. The project is on schedule to become
a LEED Silver project and meets the Energy Policy Act of 2005 energy
requirements of reducing energy consumption by 30% over the baseline
system. This is performed by utilizing a 100% outside air system and
passive style enthalpy wheels to transfer energy from the building’s
exhaust to the incoming outside air.
Tim
Barnes, Ted Cumberland, Christopher Fitzpatrick, Al Mathias, Joe Pope,
Mike Sellers - Pierce Associates, Inc.
¶
Project Name: Constitution Center, Washington,
DC
Architect/Engineer:
SmithGroup
General Contractor:
James G. Davis Construction Corporation
Constitution Center has been completely
redesigned and modernized including state of the art upgrades in HVAC
systems, façade and controls and is on track to achieve LEED
Gold certification. As part of this retrofit, Pierce Associates; sheet
metal workers from Local 100 installed $7.5 million worth of HVAC
equipment, including air handlers, heat recovery units, fan and fan
coil packages and supply and return duct systems. Also of note, they
coordinated and procured over 6,000 chilled beams to be used for building
climatization, the largest privately contracted use of these systems
in the region. All this was done in the confines of the existing building’s
structural limitations and completed in a timely fashion at the highest
industry standard.
Plumbing
John
Burroughs, Charles Gran, David Holmes, Charles Hotchkiss, John Yeatts
- Office of the Architect of the Capitol
¶
Project
Name: House Office Buildings Sprinkler Installation,
Washington, DC
AOC Construction Division plumbers expertly
performed construction to install fire suppression sprinklers throughout
the three House office buildings. Areas accessed during the construction
at the Cannon House Office Building had not been disturbed since the
building was constructed over 100 years ago. Working various hours
as to not disrupt the staff, plumbers performed work in intricate
areas and tight spaces while maintaining the architectural integrity
of the historic buildings. Workers had to deviate from proposed drawings
in order to install piping in concealed spaces to have a quality finished
product. AOC Plumbers used unprecedented methods to remove sandstone
from the original spaces to access the areas where the piping was
to be installed. The finished project exceeded all expectations.
David
Coté, Dean Feldman, Kenneth Hollingshead, Jeffery Horsmon,
Gene Sappington, Scott Styles - Pierce Associates,
Inc.
Project Name: Constitution
Center, Washington, DC
Architect/Engineer:
SmithGroup
General Contractor:
James G. Davis Construction Corporation
Constitution Center has been completely
redesigned and modernized including state of the art upgrades in HVAC
systems, façade and controls and is on track to achieve LEED
Gold certification. As part of this retrofit, Pierce Associates’
plumbers from Local 5 installed $1 million worth of plumbing equipment,
including domestic booster pumps, water heaters, sump and sewage system
and dedicated drinking systems. They also installed over 100 separate
risers servicing domestic water, storm, sewer and gas systems as well
as 900 plumbing fixtures. All this was done in the confines of the
existing building’s structural limitations and completed in
a timely fashion at the highest industry standard.
Metals
Miscellaneous
Metal Fabrication
Ruben
Cano, Francisco C. Cuevas, III, Melchor Martinez, Alexander Mendoza,
Baltazar Perdomo, Raul Salmeron - Big D Metalworks
Project Name: International
Professional Services Firm, Washington, DC
Architect: Fox Architects
/ McMurray Architectural Interiors
Engineer: Thornton Tomasetti
General Contractor:
HITT Contracting Inc.
This project included a two-story switch-back
stair, with an intermediate landing that cantilevers over a water
feature/seating area below. The stair has open risers with precast
terrazzo treads, glass railings and a continuous light fixture attached
to each stringer. The amount of coordination to calculate the unusual
torque of the stair design was extraordinary, and the execution was
flawless.
Ornamental
Metal
Steve
Ash, Joseph Perry - American Iron Works
Project Name: 1801 K
Street, NW, Washington, DC
Architect: Skidmore,
Owings & Merrill
Engineer: Girard Engineering,
PC
Structural Engineer:
Robert Silman Associates
General Contractor:
Jones Lang LaSalle Construction
The building is currently pursuing LEED-EB certification with
the USGBC. Exceptional quality and outstanding detailing took place
on the interior ornamental metals including column covers, elevator
jambs and frames.
Zdzislaw
Kiszczak, Bogdan Krenca, Waldemar Lezczynski, Xuong Hien Luc, Janusz
Mlynarczyk, Peter Perry - Soheil Mosun Limited
Project Name:700 Sixth
Street, Washington, DC
Architect: Hellmuth,
Obata + Kassabaum, PC
Structural
Engineer:
Cagley & Associates, Inc.
General Contractor:
Balfour Beatty Construction
Soheil Mosun Limited craftsmen designed,
fabricated and installed exquisite ornamental metal and glass finishes
at 700 Sixth Street. The scope of work included complicated design
and detail of all metal connections, walkways and bridge supports,
railings and other ornamental fabrications. Their craftsmanship brings
distinction to nearly every inch of the building from the interior
and exterior architectural metal grills and Chinese lanterns to the
stainless steel and glass bridge and walkway that highlight the open
lobby. The glass bridge is truly unique in that its glass floor essentially
creates a floating floor. The installation of the massive pieces of
glass and metal finishes was no light affair.
Beltran
Beita, Steve Cavanah, Ricky Gregory, Ron Jones, Darrell Keen, Ted
Thoms - Tate Ornamental, Inc.
Project Name: Georgetown
University McDonough School of Business, Washington, DC
Architect: Goody Clancy
Associates
General Contractor:
The Whiting-Turner Contracting Company
The atrium balcony and stair system railings
that Tate Ornamental fabricated and installed at Georgetown University
McDonough School of Business project is astounding. The glass and
stainless steel railing systems throughout the building atrium were
fabricated seamlessly, with high quality welds and hardware. The railing
system at the stair had a challenging attachment method at the tube
steel that runs below terrazzo treads, and also was coordinated with
the electrician for their integral light fixture and ballast installation.
The railing systems at the balconies are curved at the balcony edges
to follow the shape of the wood wall. This project has been submitted
to the USGBC for LEED Silver certification.
Structural
Steel Framing
Robert
Bading, Chet McPhatter, Jimmie Wilson - Banker
Steel Company
Project Name: Arena
Stage at the Mead Center for American Theater, Washington, DC
Architect: Bing Thom
Architects
Engineer: Fast + Epp
General Contractor:
Clark Construction Group, LLC
The renovation and expansion of the Arena
Stages performing arts campus in Southwest D.C. covered 200,000 square
feet and took 29 months. It included the creation of a new performance
arts space, the Cradle Theater, and extensive improvements to the
existing buildings. The structure’s prominent cantilevered roof
is constructed using an intricate system of roof trusses, joists and
girders which are supported by 60-foot timber columns and architectural
concrete walls. The steel trusses range in length, up to 120 feet,
and along the perimeter of the structure the trusses are supported
by the timber columns. The perimeter of the roof is curved across
multiple radiuses. Steel rafters installed along the perimeter provide
the oscillating elevation changes which combined with the radiuses,
creates a wave-like illusion. Between timber columns, steel spandrel
trusses support a cable suspension system which supports the 45-foot
frameless window wall. The steel had to be erected to tolerances as
minimal as one-quarter inch in either direction. At the west end,
a large girder is installed which cantilevers out 65 feet, creating
the dramatic canopy over the terrace.
Ruben
Herrera, Richard Johnson, Will Romero - Superior
Iron Works, Inc.
Project Name: 1999 K
Street, Washington, DC
Architect: Murphy/Jahn
Architects
Engineer: Werner Sobek
Ingenieure International
General Contractor:
James G. Davis Construction Corporation
Architecturally finished structural steel
“sail” cantilevers from concrete slab. Welded and pin
connections required extensive coordination with concrete structure
and curtain wall system, which hangs from steel “sail”.
Steel beams are tapered and therefore were shop fabricated with built-up
plates rather than pre-fabricated tube material.
Sitework
Landscaping
(interior
& exterior)
Underpinning,
Foundations and Excavations
Gene
Craig, Fabian Lehmann, Herman Ward, Tom Ward - Schnabel
Foundation Company
Project Name: The American
Trucking Associations - Capitol Hill Legislative Offices, Washington,
DC
Architect: RTKL Associates
Inc.
Engineer: Tadjer Cohen
Edelson Associates, Inc.
General Contractor:
Forrester Construction Company
The American Trucking Association sheeting
and shoring work included dealing with the zero-lot lines of neighboring
properties; maintaining extreme sensitivity to the main power supply
lines of heat and electricity to the U.S. Capitol nearby; supporting
two surrounding buildings maintaining deflection within loose sandy
soils and hard clay; and supporting three structures in midair during
construction of a parking garage below. To support the three structures,
engineers developed a design of micro piles, needle beams and soldier
piles. The sheeting and shoring system was installed over, around
and through the existing structures to support them and connect them
to the base shoring system to maintain stability during excavation
and construction. It was challenging to remove the shoring system
to replace it with the foundation system, while still supporting the
other buildings. Over 100 tons of steel was used on this project and
it took nearly seven months to install and excavate down to sub grade.
Special
Construction
Elevators,
Escalators and other Conveying Systems
Other
Historic
Preservation
Sefik
Civic, Wilfredo Fuentes, Naser Hasadzinovic, John Minihane, Timothy
Schwind, Jr., Timothy Schwind, Sr. - Worcester
Eisenbrandt, Inc.
Project Name: Chinese
Community Church Tower and Restoration, Washington, DC
Architect: Rippeteau
Architects, PC
Engineer: Robert Silman
Associates
General Contractor:
Worcester Eisenbrandt, Inc.
This project required the gentle removal
of 20th Century cover-up material, on-site evaluation of historic
fabric, brick, timber and glazing; close coordination with architects;
and integration of new work with historic remnants in winter weather
on a tight downtown site.
Infrastructure:
Utility & Roadway
John
Addison, Mike Collins, Hank Miller, Bill Schuster, Donnie Smith, Mark
Valentine - Flippo Construction Company, Inc.
Project Name: The Yards
at Southeast Federal Center Infrastructure, Washington, DC
Architect: Shalom Baranes
Associates
Engineer: VIKA, Inc.
General Contractor:
Flippo Construction Company, Inc.
Flippo Construction conducted roadway demolition,
and installation of nine roadways, storm water management systems,
electric and communication duct banks for PEPCO and Verizon, curb
and brick gutter, three surface parking lots, and a marketing tent.
Flippo installed over three miles of utility piping and over 16 miles
of conduit. The site provided over 8,000 tons of unforeseen underground
concrete obstructions and over 27,000 tons of contaminated soils.
Crews also encountered an abandoned steam line tunnel that ran for
over 1,200 feet and an abandoned water intake cooling tunnel that
ran for over 560 feet. Flippo met tight deadlines required in part
by the Major League Baseball season.
Sewer
Relining
Dan Cassel, Jason McAnally, Salvatore
Parades, Datta Shirodkar - Boyer, Inc.
Project Name: 401 M
Street, SW / Waterfront, Washington, DC
Architect: Shalom Baranes
Associates
Engineer: Tadjer Cohen
Edelson Associates, Inc.
General Contractor:
Clark Construction Group, LLC
Boyer’s craftsmen installed the 800-foot
lining which traversed two manhole to manhole sections and a short
radius 90 degree curve. The sewer system discharges to the Potomac
River roughly 1,000 feet downstream from the Waterfront project. To
place the new liner, Boyer installed an inflatable pipe plug on the
downstream end of the sewer to prevent back-water from entering the
work area. Throughout the project, the sewer system remained active.
Workers had to be prepared to remove equipment and leave the tunnel
at a moment’s notice. After the new system was installed, Boyer
used a high-strength cementitous grout to fill the annular space between
existing sewer and the PVC liner.
Scaffolding
and Rigging
Thermal
and Moisture Protection
Dave
Baker, Jose Gonzalez, Carlos Moreno, Dave Morgan, Elias Pineda
- Calvert Masonry, Inc.
Project Name: 401 M
Street, SW / Waterfront, Washington, DC
Architect: Shalom Baranes
Associates
Engineer: Tadjer Cohen
Edelson Associates, Inc.
General Contractor:
Clark Construction Group, LLC
Calvert Masonry fabricated and installed
the terra cotta rain screen cladding system that was implemented on
the North and East elevations of both Waterfront buildings. The system
consisted of 1 9/16-inch thick ceramic clay tile panels on the exterior
face with air space and mineral wool cavity insulation between the
panels and building substrate. Overlapping horizontal joints between
panels prevent driving rain from entering the cavity, yet allow air
flow upward within the cavity to assist in keeping it free of trapped
moisture and heat. This project incorporates over 11,000 body terra
cotta panels from the second floor up consisting of 11-inch, nominal
height flat panels of three separate colors and a ribbed panel profile
of a fourth color. These panels are installed in up to five-foot lengths.
In addition, over 1,500 glazed terra cotta panels are installed below
the second floor. The aluminum support system required a high degree
of layout and coordination with existing substrate and opening systems.
Calvert’s crews worked hard to ensure the proper spacing and
alignments for vertical joints in up to 70 feet of continuous run
and horizontal joints up to 125 feet of continuous run. Over 16,000
feet of horizontal aluminum framing and over 13,000 feet of vertical
framing were installed on the project.
Woods
& Plastics
Architectural
Millwork
Adam
Erdley, Joe Fleck, Jason Hunter, David Lee, Jim McAllister, Matt Moore
- ISEC, Inc.
Project Name: Howard
Hughes Medical Institute Headquarters Expansion - Phase II, Chevy
Chase, MD
Architect: Bowie Gridley
Architects
General Contractor:
Clark Construction Group, LLC
The woodwork on the Howard Hughes Medical
Institute Headquarters is extensive. Natural finish, quarter sawn,
select maple was chosen as the species for all hardstock material,
while quarter sawn English sycamore was chosen for all veneered items.
The project woodwork elements include standing and running trim throughout
the entire expansion, wood sills, wood light shelves at every window,
wood casework, shelving, cabinetry, doors, decorative glass/wood window
wall screens, feature wood wall and ceiling paneling, as well as many
other miscellaneous features such as wood handrails, stair stringers
and wood trim. The woodwork is specified to be American Woodwork Institute
(AWI) Premium Grade certified, which is the highest level of quality
possible in the AWI standard.
Tony
Barbery, Joel Cabanban, Wayne Libby, Roger Parker, Mike Pullen, Wade
Sampsell - Gaithersburg Cabinetry and Millwork
¶
Project Name: The
Jefferson Hotel Renovation & Revitalization, Washington, DC
Architect: ForrestPerkins
General Contractor:
SIGAL Construction Corporation
Gaithersburg Cabinetry and Millwork installed
a variety of paint and stain grade millwork throughout the basement
and first floor of the hotel. Their work included paint grade wall
panels with silk inset panels and hidden doors at the meeting rooms,
mahogany casework, wall panels, shelving and concealed shutters in
the library; and historic heart pine wall panels and casework in the
Private Dining Room. Due to elaborate detail, the work required extensive
coordination with the other trades. Renovation of structure with existing
walls and slabs that were out of square and level, along with numerous
ceiling conflicts and obstructions, created challenges that required
rework of the millwork details to create a cohesive structure.
Star
Award Winner for Visual Excellence
Dominic
Giovinazzo, Jose Murillo, Hanh Nguyen, Kenneth Ramey, Jim Short, Bert
Ward - Jefferson Millwork & Design, Inc.
Project Name: College
Board, Reston, VA
Architect: A2 Design,
Inc.
General Contractor:
HITT Contracting Inc.
Jefferson Millwork Design did an exceptional
work in the fabrication and installation of the millwork at the College
Board, providing the all of the millwork for the project under AWI
premium grade standards. Most of the unique millwork begins at the
entry level, 9th floor, “Sky Lobby”. Jefferson sat with
designers in the submittal process to ensure proper interpretation
of the designer’s intent and offered insights. For example,
during the show drawing process it was determined that the Pivoting
Wall Server would be too heavy if it was built with steel, so Jefferson
presented a design using an interior Trespa structure which was an
ideal substitution. For the elevator lobby, Jefferson installed stainless
steel wrapped base, lacquered MDF panels on the walls and ceiling
and SS fins that bordered the panels, drywall and elevator frames.
The Sky Lobby reception desk features the same Bendheim triple-paneled
laminated blue glass that can be found on the base building’s
“Street Lobby”. This glass is framed with custom SS channel
that houses a ¼-inch and ¼-inch glass blade. The desk
consisted of lacquered MDF panels, African Mohogany elements and a
Trend Q Stone countertop. Tables are made from bent aluminum panel,
colored 3form is attached by flush mounted SS standoffs. The wall
adjacent to the café seating also features back-painted glass
and a 3form backsplash. The conference room is bordered by ten foot
high swinging millwork doors which close and interlock together as
a continuous wall which is covered by fabric panels in the interior
of the room and locked in place with dust proof strikes. Jefferson
contributed to LEED certification by documenting the recycled content
materials and using low-VOC adhesives.
Pat
Kelly, James Maldenaldo, Tony Maldenado - The
Washington Woodworking Company
Project Name: Jones
Day, Washington, DC
Architect: Lehman Smith
McLeish
Engineer:
TOLK, Inc.
General Contractor:
HITT Contracting Inc.
The atrium alone is reminiscent of a glass
cage. It includes a stone fountain with a glass entry leading to the
servery. The servery is all white glass panels with lacquer/stainless
steel cabinets and Corian tops which all comes together as one.
Gary
Connor, Grant Ferrin, Kim Sharp, Randy Smith, John Soderquist, Tyler
Talbot - Fetzer Architectural Woodwork
Project Name: Georgetown
University McDonough School of Business, Washington, DC
Architect: Goody Clancy
Associates
General Contractor:
The Whiting-Turner Contracting Company
The elliptical wood wall in the atrium is
one of the most stunning design features of the Georgetown University
McDonough School of Business. The fire-rated wall follows the elliptical
curve of the storefront for four stories, and also follows a diagonal
line from top to bottom. Two species of wood veneer were used to create
a slight checkerboard feel to the wall. Detailing and fabricating
the wall took a lot of time and effort with astonishing results. This
unique design feature will wow all who enter this building. The high
quality craftsmanship is also apparent in the work on the curved classroom
desks and two-story sliding doors in the auditorium. This project
has been submitted for LEED Silver certification.
Casework
and Laminates
Rough
Carpentry
(including
timber construction)
|